a engineer has started to create a model in 27 days. 1/6 of the model is complete. how many days will it take to complete the model?

Respuesta :

kkelly69 kkelly69
  • 11-01-2020
It would take 22 1/2 days:

1/6 of 27= 4.5 days

4.5x5= 22.5
Answer Link

Otras preguntas

how mANY PLANTES are there
What do you need to know to describe velocity?
Which of the following makes up the dense outer layer of bone? a. compact bone b. spongy bone c. bone marrow d. periosteum
what is 3 times sqrt 18
A garden table and a bench cost $985 combined. The garden table costs $35 more than the bench. What is the cost of the bench?
The energy required to completely separate the ions from a solid is (A) free energy (B) lattice energy (C) kinetic energy (D) activation energy (E) ionization e
Evaluate the expression, using the given value of the variable. z ÷ 2 – 4z + 3(z – 3) when z = 8     A.
How many letters are their in the alphabet
2/3 of a some of money is 48p. What is 5/8 of the sum of money?
Wat do Shang artifacts reveal about this civilization.......I need help please