if 3 people can complete a job in 4 days, how many days will it take to complete the job with 5 people?

Respuesta :

briangetalla briangetalla
  • 12-12-2020
2.4 days because 3x4=12/5 =2.4
Answer Link

Otras preguntas

Divide. Simplify your answer and write it as a proper fraction or as a whole or mixed number.1/8 ÷-1/4
What did African Americans gain during WWII?
Is water a compound?
A stone thrown horizontally at a speed of 5m/s from the top of a cliff 78.4m high. A. How long does it take the stone to reach the bottom of the cliff? B. How f
how were the native Americans different from the first americans?
Which aspect of a chemical reaction is affected by an enzyme
A sports agent made one million dollars by charging a 12.5% commission to negotiate a long-term contract for a professional athlete. Find the amount of the cont
What is 5.242 rounded to nearest tenth?
How would I draw a model to find the quotient of 2.4 divided by 3.  What is this quotient ?
how were the native Americans different from the first americans?